Saraya Resort Lombok

Development Timeline

Track the progress of Saraya Resort from master planning through to completion. Our timeline updates automatically as each phase progresses.

Overall Progress20%
Last updated: February 2026

Base Programme (Conservative)— Includes full contingency for testing, certification, operational readiness, and soft opening. Practical completion by January 2028.

  • Infrastructure contingency period
  • Testing and approvals
  • Minor rectifications

Parallel activities

  • Ordering construction materials
  • Procurement of long-lead items
  • Foundation preparation
  • Villa contractor scheduling

Programme Notes

The development timeline includes a conservative base programme with built-in contingency for commissioning and operational readiness. Based on completed design, parallel construction, and procurement strategy, Saraya may achieve practical completion ahead of the base programme. All dates are indicative and subject to construction sequencing and approvals.